03-98
5. Completion Date;
6. Construction Cost;
7. Names of Major Subcontractors;
8. Square Footage;
9. Foundation Type;
10. Number of Levels;
11. Length of Design Effort;
12. Length of Construction; and
13. A list of all consultants and all proposed major subcontractors.
Also include experience in meeting the completion schedule,
awards, and major equipment suppliers and their qualifications for
similar Design-Build projects.
E. Detailed Schedule and Narrative:
The Offeror shall provide a detailed
schedule and narrative, indicating specific dates for each step of the
process:
1. Contract progress schedule:
The progress schedule will be in a time
scaled bar graph format.
The horizontal axis will be scaled for time
beginning with the Notice to Proceed and concluding with contract
completion.
The vertical axis will show the milestones and major
portions of the contract work.
All schedule items will show a start
date and a completion date;
2. The Offeror shall describe in a written narrative its plans for
phasing the work so that the Medical Center remains operational while
utilities and access roadways are realigned.
The narrative will also
detail how the contractor intends to prepare the site, disassemble,
relocate, reassemble, and reactivate utility services to the Medical
Center within the specified time limits;
3. The Offeror shall clarify its intended uses of portions of the site
for materials staging, temporary trailer offices, employee parking,
and other activities;
4. The Offeror shall specify how much allowance has been made for bad
weather in the schedule;
5. The Offeror shall specify the days of the week and the hours of
construction operations during each phase of the work; and
6. The Offeror shall specify the percentage of contract completion that
will be achieved at the completion of design and thereafter at each
month of construction.
F. CADD Drawings:
The Offeror shall submit all drawings in both hard copy
and electronic form in AutoCAD Version ______.
7
Attachment