b. Architect;
c. Structural Engineer;
d. Mechanical (HVAC, Plumbing/Sanitary, and Steam Generation)
Engineer;
e. Electrical Engineer;
f. Interior Designer;
g. Construction Project Manager;
h. Construction Superintendent;
i. Certified Industrial Hygienist; and
j. Qualified Fire Protection Engineer.
2. The Offeror shall demonstrate techniques for maintaining on-time
schedule performance;
3. The Offeror shall demonstrate a plan for utilizing the staging area,
indicated on site drawings; and
4. The Offeror shall demonstrate techniques for maintaining workmanship
and material quality control.
B. Past Experience - The Offeror shall demonstrate prior corporate
experience listing only projects awarded within the last five years with
either of the following criteria: 1) projects completed by a DB contract
(DB as defined by the VA (See article A1.2), and 2) project was one
similar in size and scope to this project.
Scoring may be more
favorable if both criteria are met.
Also include the following
information for each project listed (Items are of equal importance):
1. The Offeror's design experience in the Design-Build process;
2. The Offeror's construction experience in the Design-Build process;
3. The Offeror's recent experience in meeting the completion schedule
for similar projects;
4. The Offeror's awards that have been won for similar projects; and
5. The Offeror the major equipment supplier and their qualifications.
C. Schedule - The Offeror shall provide a detailed schedule with narrative:
1. Design Period:
a. The design period and provisions for Government reviews;
b. A list of drawings to be included with each design submittal for
VA reviews; and
c. A phasing plan for coordination of interruptions to the utility
service due to relocation site utility work.
2. Construction Period:
b. Demolition method and sequencing;