4. CRITICAL PATH METHOD (CPM)
If required, submit the following including VA comments from previous phasing
meetings and DD2 review:
a. Phasing Narrative.
b. Phasing Diagram drawn on the Phasing Plan.
c. Full size contract drawings for the CPM Phasing Plans (one drawing may
reflect several reduced site plans)
d. Written list of systems, including temporary system by phase, and separated
by technical discipline.
5. ELECTRICAL
a. Submit 100 percent complete drawings including complete legend symbol
list, details, and schedules.
b. Show all new services to buildings, all new high voltage cable installations,
all manholes, ductlines, transformers, street lighting, grounds lighting, and the high
voltage service point on the electrical plot plan.
c. Complete the one-line riser diagram including all conduit, cable, ground wire,
and equipment sizes. Indicate nominal transformer impedance. Show
panelboards schedules. Provide signal, telephone, security, and fire alarm risers;
identify all devices and locations.
d. Complete the building electrical floor plans. Indicate all lighting and power
circuit systems. Show motor protective devices, controller and feeder sizes. Locate
all panels, transformers, and other major electrical components.
e. Provide final calculations.
f. Provide written approval by the utility company of the design of the electrical
incoming service. Furnish copies of pertinent correspondence.
g. Submit electrical specifications in format provided in CD1, paragraph 16,
SPECIFICATIONS.
Program Guide, PG-18-15, Volume B
Construction Documents 1
May 2006