b. Submit final calculations and narrative.
c. Submit plumbing specifications in format provided in CD1, paragraph 16,
SPECIFICATIONS.
13. SANITARY
a. Submit 100 percent complete and coordinated drawings to include the
following:
1) Previously submitted drawings that have incorporated comments of the
last review;
2) Irrigation system at the same scale as storm sewer drawings;
3) Sizes and invert elevations of storm and sanitary sewerage systems;
4) Profiles of storm and sanitary sewers; and
5) Legend, notes and details.
b. Submit final calculations and narrative.
c. Submit sanitary specifications in format provided in CD1, paragraph 16,
SPECIFICATIONS.
14. SITE DEVELOPMENT
a. Submit 100 percent complete and coordinated site and landscape contract
drawings. Expand the approved DD2 drawings to the level of detail necessary for
construction. Any deviation from the approved drawings at this point must be
approved by the VA project manager.
b. Submit site development and environmental specifications in format
provided in CD1, paragraph 16, SPECIFICATIONS.
15. SPACE PLANNING
Submit updated space accounting summary table.
16. SPECIFICATIONS
a. Submit for all technical disciplines the original VA Master Specification
section drafts marked-up with pencil showing the editing for the project. Clearly
identify modifications, deletions and insertions. Assure the specification drafts have
been edited and tailored in their application to represent accurate coordination
between drawings and specifications.
Program Guide, PG-18-15, Volume B
Construction Documents 1
Page 50
May 2006