CP 7 -- Continued
(4) Approved or disapproved shop drawings and manufacturers' literature shall
be distributed as follows:
(a) The original reproducibles received from the Contractor will be retained
by the A/E.
The A/E shall reproduce two direct photographic paper reproducibles from the checked
reproducibles for transmittal to the Resident Engineer. The Resident Engineer will retain
one reproducible and transmit the other to the Contractor.
(b) One set of approved or disapproved manufacturers' literature shall be
retained by the A/E. Three sets will be transmitted to the Resident
Engineer who will retain one set and forward two sets to the Contractor.
(5) The A/E shall retain approved and rejected reproducibles, manufacturers'
literature and correspondence on these items only until contract completion.
(b) Master Specification Section S, "Samples and Shop Drawings" contains the
instructions to the Contractor in reference to submittals.