c. Submit a planting plan with list of suggested plant materials for various
landscaping needs, such as, open area plazas, courts, atriums, entryways and other
various exterior/interior features. Indicate proposed materials to be used for each
element. Show planting irrigation areas.
d. Submit topographic, utility and landscape survey drawings prepared during
the schematic design phase.
e. Indicate locations of accessible parking spaces and number of handicapped
van driver parking spaces on site plan.
15. SPACE PLANNING
Submit updated Space Accounting Summary Table. Justify in writing substantial
deviations from the approved space program.
16. SPECIFICATIONS
a. Comply with the requirements of the VA Manual for Preparation and
Issuance of Construction Solicitation and Contract Documents.
b. Obtain Master Construction Specifications from VA as explained in the
Manual described above.
17. STEAM DISTRIBUTION (OUTSIDE)
a. Refine the load calculations for steam and condensate, and pipe sizing
calculations. Submit all calculations.
b. Show final location of distribution systems on a plot plan. Include location of
all manholes and pipe expansion devices.
c. Provide plan views and sections of manholes, trenches, and tunnels
showing overall dimensions and arrangement of major piping.
d. Submit test report on soil conditions related to classification of factory-
fabricated pre-engineered underground systems.
18. STEAM GENERATION
a. Show final location of new steam generating facilities on a plot plan.
b. Select all major equipment including boilers, pumps, heat recovery devices,
tanks, and emissions control devices.
Program Guide, PG-18-15, Volume B
Design Development 1
May 2006
Page 31