11. INTERIOR DESIGN
a. Illustrate fully developed design solutions for all special spaces identified at
S2. Include reception counters and desks. Include "roughs" of elevations,
perspectives, or plans as needed to clearly indicate your intentions.
b. Show wayfinding, floor and wall patterns, lighting and signage, handrails and
bumber guards, and other interior architectural elements designed to function with
and articulate the interior design solution.
c. Complete Specification Section 09050 for all materials and products used in
the design solution for all special spaces.
d. As a typical example, complete a finish schedule entry for each of all special
spaces. Fill in the material and color codes columns consistent with the design
solution.
e. Submit one set of sample boards. Include an actual sample of all materials,
finishes, or products with a color, texture, or pattern.
f.
Insure all documents are coordinated. Be consistent.
12. PLUMBING
a. Submit 1:100 (1/8-inch) scale floor plans that will be construction drawings.
Identify new plumbing fixtures and existing plumbing fixtures that will be affected by
new construction. Identify new medical gas and laboratory gas outlets. Add new
b. Provide current design narrative.
13. SANITARY
a. Indicate invert elevations of trunk sewers and approximate size of all pipe
indicated on S2 drawings. Add building service piping and new equipment.
b. Submit calculations and updated narrative.
14. SITE DEVELOPMENT
a. Submit site plans including demolition, locations of structures, parking,
roads, service areas, walks, plazas, buffers/tree groupings, landscape screening,
and other site/building features.
b. Submit a grading plan including existing and proposed contours at 500 mm
(2 foot) intervals of the entire area affected by the site work. Show spot elevations
at structure corners, entrances, equipment pads, other critical areas, and all first
floor elevations.
Program Guide, PG-18-15, Volume B
Design Development 1
Page 30
May 2006