gravesite monumentation grid and the outline of all burial sections with gravesite
yield.
e. Completed subsurface investigation report for road design.
f. Substantially completed details for all construction. Show construction
g. Signage layout plan, signage schedule, construction details and sign face
graphics, substantially complete.
h. Planting plan, substantially complete, with symbols showing location of all
trees, shrubs, planting beds and lawns. A complete planting list and planting details
should be provided with common name, genus and species, size/caliper and
special comments at a minimum. The plants shall have been checked for suitability
to the micro-climate and availability.
i. Submit topographic, utility, and landscape survey drawings as submitted for
Design Development 1 (DD 1).
2. ARCHITECTURAL
a. Submit floor plans at 1:100 (1/8 inch) or 1:50 (1/4 inch) scale that show
partition thickness, chase walls, room titles, door size and swings. The plans are to
be revised per comments from previous submittal and further developed.
Dimension corridors and stairs. Indicate and identify plumbing fixtures and fixed
equipment, shelving, casework etc.
b. Show all floor drains and indicate the pitch of floor to drains on the 1:100
(1/8") architectural plans only.
c. Indicate all fire partitions, smoke partitions; safety and protective elements.
d. Submit reflected ceiling plans at 1:100 (1/8 inch) for entire building
indicating ceiling mounted equipment, lighting fixtures, air diffusers, registers, return
air grilles, acoustical tile grids, etc. Show ceiling heights on these drawings.
e. Submit exterior elevations that have been further developed and revised per
comments from previous submittal. Show story height, penetrations, materials,
architectural screens, roof enclosures, skylights, stacks and breechings on
elevations as applicable. Show finish grades and relevant existing grades at
corners, entrances, platforms and ramps.
f. Submit 1:50 (1/4 inch) scale equipment floor plans with revisions per
comments from previous submittal. All equipment should be identified and
coordinated with VA's Equipment Guide List, Program Guide 7610 (Chapters 701
Program Guide, PG-18-15, Volume D
June 1999
Page 28