7. PLUMBING
a. Incorporate all comments from the last review and submit current design
narrative.
b. Submit 1:100 (1/8-inch) scale floor plans (P-Series) that will be construction
drawings. Indicate exceptions at a scale of 1:50 (1/4 inch). Identify new plumbing
fixtures and existing plumbing fixtures that will be affected by new construction. Use
VA fixture numbering system. Add new equipment.
8. HEATING, VENTILATING & AIR CONDITIONING
a. Provide a single-line preliminary layout of the HVAC ductwork and piping.
HVAC equipment can be designated with a block layout. Indicate approximate
sizes and establish ceiling clearances.
b. Provide preliminary support calculations.
9. ASBESTOS ABATEMENT
Where asbestos abatement is required, submit asbestos abatement drawings
and substantially complete assessment report in accordance with VA guidelines for
asbestos abatement.
10. ELECTRICAL
a. Contact the electrical utility that will supply electrical power to the cemetery.
Modify the previous submission documents to meet the utility company's
requirements. Submit a written summary of any conversations with the electrical
utility.
b. Show preliminary sizes of major electrical components on the one-line
diagram of the proposed high voltage system, low voltage system, and emergency
system (if required) insufficient detail to allow a review discussion.
c. Provide preliminary updated load calculations.
d. Show tentative locations of the components of the high voltage system,
that may be critically influenced by space or locations considerations.
e. Show existing or demolition work by dashed lines.
11. COST ESTIMATING
Program Guide, PG-18-15, Volume D
June 1999
Page 26