(2) Phasing Plans (on reduced site plans).
(3) Phasing Diagram.
(4) Phases marked on all full size drawings submitted for VA review.
(5) Written list of systems, including temporary system by phase, and
separated by technical discipline.
B. SCHEMATICS 2 [S 2]
1. SITE DEVELOPMENT AND ENVIRONMENTAL
a. The VA-selected alternative from Schematics 1 or the VA provided concept
plan will be the basis for further development for this submission. The A/E may
deviate slightly from the selected alternative only after receiving approval of the VA
Project Manager.
b. Drawings for this submission will depict site features with more detail than
the previous submission.
c. Submit a narrative concerning the project development since the previous
submission. Include a phasing analysis, if required, of sequencing construction
activities to avoid conflicts with the routine cemetery operation.
d. Submit the topographic, utility, boundary, and landscape surveys.
e. With these surveys as a base, submit proposed building locations,
demolition, proposed roads, parking, interment areas, entrances and exits, and all
mechanical and electrical components on grade. Consider function, aesthetics, and
preservation of natural features and topography when locating all elements/features.
f. Submit grading plans of all proposed construction. Show spot grades at
structure corners, entrances, intersections, etc. Provide first floor elevations for
structures and equipment pads.
g. Show erosion and sedimentation control, storm water management,
drainage, staging areas, construction access and parking, and stockpile areas for
earth and materials.
h. Submit landscape drawings showing plant groupings and a list of proposed
plant materials.