III. CRITICAL PATH METHOD (CPM) PHASING MEETINGS
A. If required, and prior to submission of Schematic 1 material, the A/E shall
meet with the VA Project Manager and VA representatives of the Critical Path
Method Service (CPM) and the National Cemetery Administration to discuss and
outline phasing requirements for the project. These phasing requirements shall
describe the general sequence of the project work, estimated project duration, and
what Government constraints will exist that will influence the Contractor's approach
to the construction project. The A/E shall be responsible for recording the phasing
requirements.
B. The A/E shall submit a phasing narrative and phasing plans (on reduced
size plans) within two weeks after each phasing meeting to the VA Critical Path
Method Service. The CPM staff will review these submission(s) and return
comments to the A/E within two weeks of receipt. The A/E will then use this
information in preparing their schematic, design development and construction
document submissions.