June 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
SCHEMATIC 2 (S2)
REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Check if the A/E submission is in compliance with PG-18-15.
2
Summary of PG-18-15 A/E submission requirements for the designers:
a. Provide description of HVAC systems and equipment for each
functional space.
b. Provide complete life cycle cost analysis with specific
recommendations and full back-up data.
c. Provide heating and cooling capacities of each functional area, and
bloc loads for each building.
d. Indicate tentative locations and sizes of all mechanical equipment
rooms, and main shafts.
e. Show block layouts of major pieces of equipment.
f. Resolve locations of louvers. Outside air intake louvers must be
away from loading dock and truck waiting areas, and emergency
3
Check compliance by the designer, requirements stated in the applicable
VA, HVAC Design Manual.
4
Compliance with VA National CAD Standard Application Guide and
applicable National CAD Standard modules.
9