June 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
DESIGN DEVELOPMENT 2 (DD2)
COMMENTS/
NO.
ITEM
YES/NO/NA
2
l. Provide updated 1:50 (") scale typical mechanical equipment
(cont.)
room plans by incorporating previous comments.
m. Provide updated controls, flow and control diagrams.
n. Provide sound/acoustic analysis to ensure compliance with the
HVAC Design Manual.
o. Provide demolition drawings indicating scope of work for
demolition.
q. Show outside chilled and condenser water piping. Show how the
pipes will be laid.
r. Show scope of work for ECC, its planned capabilities, and point
schedule.
s. Submit several sample specification sections of VA Master
Specifications edited with pencil to reflect scope of work of the
project. Provide a list of all sections that will be required for the
project.
3
Check compliance by the designer requirements stated in the applicable
VA, HVAC Design Manual.
4
Check smoke and fire protection, and other life safety provisions in the
design:
5
Compliance with VA National CAD Standard Application Guide and
applicable National CAD Standard modules.