June 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
DESIGN DEVELOPMENT 2 (DD2)
REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Check, whether the A/E submission is in compliance with PG-18-15.
2
Summary of PG-18-15, A/E submission requirements for the designers:
a. Provide first detailed version of room by room heating and cooling
loads accompanied by architectural drawings showing each zone,
floor areas, and room schedules showing coordination between
architectural room numbers, and coded room numbers used for
computer input.
b. Provide input manual for computer program used.
c. Provide derivation of "U" values, and window data for heating and
cooling loads.
d. Update these calculations during subsequent design phases to
reflect all changes.
e. Include calculations for review: Peak zone by zone heating and
cooling loads; Building block loads; Estimated steam consumption
from all sources; Psychrometric chart of each air handling unit;
and Room by room air balance charts for each air handling unit.
f. Submit selection of major pieces of equipment with catalogue cuts.
g. Ensure coordination with other disciplines and provide pertinent
information required by them.
h. Submit 1:100 (1/8") scale HVAC floor plans for typical areas
showing at least duct mains with sizes based on updated
calculations. All ductwork and piping larger than 150 mm (6") to
be in double line.
i. Provide local cross sections showing HVAC work and clearances
in 1:50 (") scale.
j. Indicate individual room air distribution and temperature controls
for representative samples of typical spaces.
k. Provide separate floor plan drawings for ductwork and piping,
unless waived by VA.
12