JULY 2005
SOLICITATION FOR OFFERS
OUTPATIENT CLINIC
SFO NO. V101-183R-xxx-xxx-xx
[INSERT LOCATION OF FACILITY]
Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of
work.
Increase the number of working hours per shift, shifts per working day, working days per week, the
amount of construction equipment, or any combination of the foregoing to eliminate the backlog of
work.
Reschedule the work in conformance with the solicitation requirements.
The Lessor shall notify the Contracting Officer or designee concerning what actions are being taken to
mitigate the proposed schedule changes. The project schedule revisions shall be incorporated by the
Lessor into the network diagram before the next update, at no additional cost to the Government.
3.25.2 REVISIONS TO SCHEDULE:
Within 10 calendar days after any project progress schedule update, the Lessor shall submit a revised
project schedule for any of the following reasons:
Delay in completion of any activity/event or group of activities/events that indicates an extension of the
project completion by 20 working days or 10 percent of the remaining project duration, whichever is
less. Such delays, which may be involved with contract changes, strikes, unusual weather, and other
delays, will not relieve the Lessor from the requirements specified unless the conditions are shown on
the schedule as the direct cause for delaying the project beyond the acceptable limits.
Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the
work necessary.
The schedule does not represent the actual prosecution and progress of the project.
Project schedule revisions made under this paragraph which affect the previously approved
computer-produced schedules for Government furnished equipment, contract phase(s) and sub-phase(s)
or any other previously contracted item, must be furnished in writing to the Contracting Officer or designee
for approval.
3.25.3 APPROVAL OF SCHEDULE:
The Contracting Officer or designee approval for the revised network diagram and all relevant data is
contingent upon compliance with all other paragraphs of this section and any other previous agreements
by the Contracting Officer or designee.
3.25.4 COSTS OF REVISIONS:
The cost of revisions to the network diagram resulting from contract changes will be included in the
proposal for changes in work as specified in Paragraph 3.8, Contract Changes, of this Solicitation, and will
be based on the complexity of the revision or contract change, man hours expended in analyzing the
change, and the total cost of the change.
The cost of revisions to the network diagram not resulting from contract changes is the responsibility of the
Lessor.
3.26 CONSTRUCTION OBSERVATION:
Observations of the work during construction will be made periodically by the Contracting Officer and/or
the designated Contracting Officer's Technical Representative (COTR) to review compliance with the
Solicitation requirements and the final working drawings.
Part I: Basic Solicitation Requirements Page 39 of 169
Lessor __________ Gov't. __________
__________ of __________ Pages