SPECIAL PROVISIONS
ARTICLE F
SUBMISSION AND COMPLETION SCHEDULE
SPF 1
REVIEW AND COMPLETION SCHEDULE
(a) During the process of the work the Contracting Officer will conduct periodic
reviews with the A/E. The A/E shall perform the work required within the limits of the
following schedule. Professional Architects, Engineers and related design disciplines
familiar with the work shall be provided, as directed by the Contracting Officer, to attend
the VA reviews in the Washington, DC office of the Contracting Officer and/or at the
medical center.
SUBMISSION AND COMPLETION SCHEDULE
ITEM
DATE
SCHEMATIC DESIGN
Deliver Material to VAMC and Contracting Officer
not later than .......................................................................
?
Review Material with VAMC on .............................................
?
Review Material with Contracting Officer on ............................
?
(Payment not to exceed 35% of the total contract amount
at the completion of the review material)
REQUEST FOR PROPOSAL
Deliver Material to VAMC and Contracting Officer not later than
?
Review Material with VAMC on .........................................
?
Review Material with Contracting Officer on ............................
?
(Payment not to exceed 65% of the total contract amount
at the completion of the review material)
Mail Request for Proposal Notice on ...............................................
?
Issue Request for Proposal Documents to Proposers on...........................
?
Proposal Receipt Date ...............................................................................
?
Design Build Contract Award .............................................................
?
Design Build Completion ....................................................................
?
1