SPG 5
MONTHLY DESIGN PROGRESS REPORT
By the fifteenth day of the reporting month the A/E shall submit to the Contracting
Officer a progress report (See CP 2).
SPG 6
SEAL OF A/E
Each Contract Drawing shall bear the seal and signature of the registered
professional architect or engineer responsible for its design. The seal and signature
shall be affixed for the final scheduled review stage of each phase of the
Construction Documents section. Before the final contract documents are issued for
bidding, a principal of the A/E firm under contract to the VA will be required to
provide a signed certification that all drawings and calculations have been properly
signed and sealed by the appropriate individual for each discipline, in accordance
with the rules and regulations of the local State licensing authority. This
certification shall be forwarded to the Contracting Officer upon the completion of the
Contract Documents.
SPG 7
SIGNATURE OF CONTRACTING OFFICER
The A/E shall deliver the original Contract Drawings to the Contracting Officer
for his signature after all final review comments have been considered and
incorporated into the work prior to printing of and issue for construction bidding.
SPG 8
CERTIFICATE OF INTEREST
The A/E shall submit a certificate with the final scheduled working drawing
submission of each phase of the project stating any interest, direct or indirect, which
the firm or any officers of the firm may have in any business or industry that
manufactures or furnishes equipment or materials that are specified for the project.