June 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
FINAL BID DOCUMENTS
REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Check if the A/E submission is in compliance with PG-18-15.
2
Summary of PG-18-15 A/E submission requirements for the designers:
a. Place the seal of the professional engineer responsible for the
design on the drawings.
b. Submit revised draft specifications to incorporate all changes,
resolution of conflicts and modifications noted at CD1 review.
Revisions shall also include results of any drawing changes not
shown on CD1 documents that affect the specifications.
c. Type specifications in final format and submit a complete set for
review. Include a set of full size final drawings fully coordinated.
d. Return all draft specifications reviewed at CD 1 review to aid the
final bid documents review.
3
Compliance with VA National CAD Standard Application Guide and
applicable National CAD Standard modules.
16