//b. TASK 2:
Perform continuous air monitoring, inspection and
testing outside the regulated area(s) during actual abatement
work to detect any faults in the regulated area(s) isolation
and any adverse impact of surroundings from regulated area
activities.
VA STAFF NOTE: Buildings which will be totally demolished after
abatement may not require Task 1 and Task 2 above by the IH/CIH
consultant.
Perform unannounced site visits to spot check overall
c. TASK 3:
compliance of asbestos abatement work with project
design/contract documents. These visits may include any
inspection, monitoring and testing inside and outside the
regulated area(s) and all aspects of the abatement project
except personnel monitoring.
Provide support to the VA representative such as
d. TASK 4:
evaluation of submittals form the abatement contractor,
resolution of unforeseen developments in abatement work, etc.
Perform, in the presence of the VA representative,
e. TASK 5:
final clearance/inspection and testing of a decontaminated
regulated area or building at the conclusion of the abatement
and clean-up work to certify compliance with VA project design
clearance/decontamination standards.
Issue certificate of clearance/decontamination for
f. TASK 6:
each regulated area or building and project report.
4. All data, inspection and testing results generated by the IH
consultant will be available to the abatement contractor for
information and consideration. The Asbestos Abatement Contractor
shall provide cooperation and support to the IH/CIH consultant for
efficient and smooth performance of their work.
5. Monitoring and inspection results of the IH/CIH consultant will be
used by the VA to issue any STOP REMOVAL orders to the abatement
contractor during abatement work and to accept or reject regulated
area(s) or a building as decontaminated. The IH/CIH consultant will
make available to the abatement contractor the plan for sample
collection and analysis for continuous monitoring outside the
regulated area(s) and the plan of final clearance inspection and
testing for each regulated area or building prior to executing each
plan. Plan will include location for samples, name and qualification
of person taking samples, whether on-site analysis and/or off-site
11