3.4 SCOPE OF WORK FOR CONSTRUCTION DOCUMENTS ABATEMENT DESIGN
A. A/E Team Other Than I.H. Consultant:
Develop Construction Documents Drawings for Abatement
1. TASK 1:
Design:
a. ACM shall be shown in the architectural drawings where general
demolition is required prior to abatement. Review HVAC and
electrical designs to ensure coordination of all work including
phasing schedules for ACM and ACE removal, re-insulation or
installation of material removed during asbestos abatement, etc.
Coordinate with VAMC and other trades of A/E to determine ingress
and egress routes and waste transport routes for each regulated
area in partially occupied buildings. In the same way, develop
emergency action plan procedures. Evaluate impact of abatement on
critical support systems such as local exhausts, compressors,
vacuum lines, fire and smoke systems, etc. Coordinate with VA
personnel to determine locations and routings of temporary
utilities for each work area.
B. I.H. Consultant:
Develop Construction Documents for Abatement Design:
1. TASK 1.
a. At the first construction documents submission. Provide separate
asbestos removal 1/8" scale drawings labeled AR. Drawings shall
show the location and quantity of all ACM and ACE in the regulated
areas and how they will be removed/abated. The AR design shall
reflect the findings and recommendation of the survey/inspection
and assessment report and shall clearly show the regulated area(s)
for each workspace, the location and configuration of the
configuration of the equipment decontamination facilities; the
number, size and location of HEPA units for each regulated area;
the path of material transportation to the loading platform; and
design. In addition, show the exact location and
size/configuration of the pipe elements to be decontaminated using
the glove bag procedure. Show the exact design for all dirt floor
abatement. Show all piping/fittings that are 4" diameter and
smaller as one size. Show all piping/fittings over 4" diameter. In
addition, differentiate among steam and water piping. Show
contamination related to ceiling and wall demolitions in order to
gain access to ACM above and beyond uncontaminated ceilings and
walls that must be removed in order to have access. Review HVAC
9