decontaminated with this project. Solicit the input of the VA
Medical Center (VAMC) for the identification of these additional
areas to be decontaminated. The plans shall be 1/8" reproducible
sepias suitable for marking up information on them. A/E to provide
a detailed description of the contemplated work in each impacted
area and participate with the IH in a thorough walk through of all
impacted spaces.
b. Identify and incorporate phasing requirements, dictated by
asbestos abatement work, into a phasing plan for entire asbestos
abatement project.
Review and Coordination of Schematic Abatement Design:
2. TASK 2.
a. Review for accuracy of impacted areas and for impact on other
trades the preliminary draft of asbestos assessment/scope of work
and abatement problems and solutions, developed by the IH
consultant, prior to its submittal to the VA.
B. I. H. Consultant:
Development of Sample Plan:
1. TASK 1:
a. If necessary, develop an asbestos sampling plan showing the
location of all proposed samples, showing existing information
such as old samples and areas that have been decontaminated by
previous abatement projects and providing the rationale of the
plan showing how the new samples in combination with the existing
asbestos survey/inspection required by the VA will enable the IH
consultant to identify with a high
location, quantity, type of, and condition of all asbestos
containing materials (ACM) and the location and quantity of all
asbestos contaminated elements (ACE) in the abatement areas.
b. The minimum work required for the development of the sampling plan
will consist of the following, if necessary:
1) Request from A/E reproducible 1/8" architectural plans of all
impacted areas to be used for identifying the exact location of
the proposed new samples and other necessary information.
2) Compile and review as-built drawings, inspections and
specifications for existing impacted facilities for
identification of ACM used in the construction of these
facilities.
3) Review previous and current abatement projects and note
information that may relate to any ACM/ACE for this project.
Mark locations of those projects on plans.
4