(4) Approved or disapproved shop drawings and manufacturers' literature shall
edistributed as follows:
(i) The original reproducibles received from the Contractor will be retained by
the A/E. The A/E shall reproduce two direct photographic paper reproducibles
from the checked reproducibles for transmittal to the Resident Engineer. The
Resident Engineer will retain one reproducible and transmit the other to the
Contractor.
(ii) One set of approved or disapproved manufacturers' literature shall be retained
by the A/E. Three sets will be transmitted to the Resident Engineer who will retain
one set and forward two sets to the Contractor.
(5) The A/E shall retain approved and rejected reproducibles, manufacturers' literature
and correspondence on these items only until contract completion.
(b) Master Specification Section S, "Samples and Shop Drawings" contains the instructions
to the Contractor in reference to submittals.