a.
Provide revisions to the design narrative and plans of utility systems indicated in
S1. Indicate (obtain from medical center staff) water pressure and flow at two fire hydrants
serving building in project and depth of cover for new water and fuel gas mains.
13.
SITE DEVELOPMENT
a.
Further develop the VA-selected alternative from S1 or the VA provided concept
plan. Slight deviation from the selected alternative is possible with approval of the VA
Project Manager.
b.
Depict site features with more detail than the previous submission.
14. SPACE PLANNING
Update and expand the Space-Accounting Summary Table. In addition to the data
required at S1, provide columns for Designed Net Area and Variance From Approved
Space Program Net Area for each department or service. Also, list separately the area
required for additions to the program, unassigned space, major circulation (inter-
departmental corridors, stairs, elevators), major mechanical and electrical spaces, exterior
walls, connecting corridors to other buildings, space for future mechanical system
expansion, and similar special requirements.
15. SPECIFICATIONS
No submission is required.
16. STEAM DISTRIBUTION (OUTSIDE)
a.
Provide a report with the following information as a minimum:
1)
Estimate of steam and condensate loads which will be imposed on new or
existing distribution facilities;
2)
Calculations of pipe sizing.
17. STEAM GENERATION
a.
Provide a report with the following information as a minimum:
1) Combined new (estimated) and existing steam loads including maximum and
minimum summer and winter demands and total annual production. Provide break-
down of new steam loads into categories of end use such as building heating,
humidification, reheat, domestic hot water, sterilization, line losses, kitchen, and
laundry;
2) Select any new major equipment and preliminary calculations of equipment
sizing.
18. STRUCTURAL
Program Guide, PG-18-15, Volume F
Schematics
Page 17
June 2006