III. DISTRIBUTION OF A/E MATERIAL
A.
SYMBOL IDENTIFICATION OF CONTRACT DRAWINGS
AS
-
Architectural Drawings (Numbered Only)
HA
-
Asbestos Removal Drawings
BI
-
Boring Log Drawings
ES
-
Electrical Drawings
FA
-
Fire Protection Drawings
MH -
Heating, Ventilating, and Air Conditioning Drawings
PL
-
Plumbing Drawings
GS
-
Site Development and Environmental Drawings
CU
-
Sanitary and Irrigation Drawings
MS- Steam Distribution Drawings
MP -
Steam Generation Drawings
SS
-
Structural Drawings
B.
GENERAL NOTES
1.
Bond prints shall be full-sized.
2.
Bind all drawings into sets in the order of their above classification symbol.
3.
All submitted specifications shall be original, unbound, and marked-up VA Master
Specifications. Where no VA Master Specification is available, submit a developed
specification.
4.
Submit all materials, packaged and clearly marked by discipline, to the VA's
Project Manager. However, where a small amount of material is submitted, the drawings may
be packaged together for all disciplines as long as the drawings are separated and tagged with
the discipline name. Other material may also be consolidated provided they are labeled and
can easily be identified and separated.
5.
Material provided unbound and/or un-separated will be returned to the A/E. All
re-submittal costs will be the responsibility of the A/E.
6.
Submit record drawings on bond paper, full size one copy and on standard
format DVD, two copies. Each of the two electronic copies shall contain .dwg and .pdf files of
each drawing, and .doc and .pdf files of each project manual document. Each DVD will be
labeled as to station #, project #, date, etc..
Program Guide, PG-18-15, Volume F
Schematics
Page 19
June 2006