O. ASBESTOS ABATEMENT: Submit the following:
Asbestos Abatement:
Schematics*
DD**
CD***
Asbestos abatement report including:
1. Summary results of building
records
2. Summary results of station
personnel interview
3. determination of materials known
to contain asbestos
4. visual inspection of building to
determine location and condition
of asbestos
5. sample strategy on the extent of
asbestos present
Name and location of qualified
laboratory for sample analysis
Asbestos abatement drawing
Major Decontamination Areas showing:
1. Limits of sealing off the location
2. Quantities of asbestos material
3. Arrangements for auxiliary rooms
4. Engineering of negative air
systems
5. Path of asbestos to loading
platform
6. Location and connection to
required utilities
Minor Decontamination Areas showing:
1. location, type, and length of pipe
element to be abated by "Glove
and Bag" approach
2. Other abatement features
Summary of:1
Square meter (feet) of floor space
for abatement
Total linear and square meter (feet)
of asbestos to be abated
Total cost of abatement2
Program Guide, PG-18-15, Volume C
37
May 2006