Department of Veterans Affairs
VA Space Planning Criteria 7610-(270)
Washington, DC 20420
September 2006
projected CWT Work Stations. (See Table 1). Provide an additional 65 NSF per
projected CWT Work Station greater than one.
3. CWT: Storage (SRS01)............................................................... 10 NSF (1 NSM)
Minimum NSF and if in Concept of Operations. Provide an additional 10 NSF per
projected CWT Work Station greater than one.
4. CWT: Toilet, Patient (TLTU1) .................................................. 50 NSF (4.7 NSM)
Provide one for male and one for female and if in Concept of Operations.
5. CWT: Evaluation Area (OTDL1)............................................ 100 NSF (9.3 NSM)
Minimum NSF and if in Concept of Operations. Provide an additional 10 NSF per
projected CWT Work Station greater than ten. Maximum of 400 NSF.
6. CWT: Patient Rest Area (OTDL1) ......................................... 100 NSF (9.3 NSM)
Minimum NSF and if in Concept of Operations. Provide an additional 8 NSF per
projected CWT Work Station greater than thirteen. Maximum of 400 NSF.
7. CWT: Office, Compensated Work
Therapy Supervisor (OFD03).............................................. 120 NSF (11.2 NSM)
Provide one per Compensated Work Therapy Clinic and if in Concept of
Operations.
K. Incentive Therapy Program (ITP)
Provide spaces below only if in authorized Concept of Operations.
1. ITP: Sub-Waiting (WRC01)..................................................... 40 NSF ( 3.7 NSM)
Minimum NSF. Divide the projected number of annual ITP Treatment Station
clinic stops by TBD to calculate the number of projected ITP Treatment Stations.
(See Table 1). Provide an additional 40 NSF per each increment of two projected
ITP Work Stations greater than two.
Provide two seats per projected ITP Work Station; allocate one at 15 NSF and
one at 25 NSF.
2. ITP: Treatment Clinic (XXYYC) ................................................. 6 NSF (0.5 NSM)
Minimum NSF. Divide the projected number of annual ITP Treatment Station
clinic stops by TBD to calculate the number of projected ITP Treatment Stations.
(See Table 1). Provide one if in Concept of Operations. Provide an additional 6
NSF per projected ITP Work Station greater than one..
3. ITP: Tool Area (XXYYC) .......................................................... 60 NSF (5.6 NSM)
Provide one per Incentive Therapy Program and if in Concept of Operations.
4. ITP: Showers, Lavatory and Watercloset (TLTP3) ............... 75 NSF ( 6.9 NSM)
Provide one for male and one for female and if in Concept of Operations.
5. ITP: Office, Supervisor (OFD03)......................................... 120 NSF (11.2 NSM)
Provide one per Incentive Therapy Program and if in Concept of Operations.
Physical Medicine and Rehabilitation Service (Chapter 270): Page 270-15 of 24