Format b
A/E's ESTIMATE OF ADJUSTMENT IN CONTRACT AMOUNT
ANALYSIS OF ESTIMATED MANHOURS FOR DRAWINGS
Sheet____of _____
ESTIMATED
TIME IN
MANHOUR
S
DWG. NO.
CODE
Technical
Designer
Draftsman
Total
Total for
ITEM NO.
LETTER 2/
(If new
Supervision
Drawing
(Circle on
Drawing 1/
Of Work
indicate thus:
"new")
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
TOTAL
1/ Submit blueprints of drawings requiring revision, indicating the portion of drawings which need revision by circling the portion(s) and
identifying each by numbering in Column (2) above.
2/ For Column (3) identify type of work by use of the following code:
A
Architectural
E
Electrical
L
Site Planning
H
Heating, Ventilating and Air Conditioning
B
Subsurface (Structural)
G
Steam Generation
S
Structural
D
Outside Steam Distribution
W
Sanitary
DE Architectural Miscellaneous Detail
Q
Equipment (Laboratory)
FS Fallout Shelters
P
Plumbing
-- Other