Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 300
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service Day Hospital
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAIN
CEILING
DOOR
H.W.NO.
SYMBOL
Staff Offices:
Office,
CP
RB
GWB-W
AT
1/2 S
23
Psychiatrist
Office,
CP
RB
GWB-W
AT
1/2 S
23
Psychologist
Office, Social
CP
RB
GWB-W
AT
1/2 S
23
Worker
Office, Resident/
CP
RB
GWB-W
AT
1/2 S
23
Trainee
Office, Rehab.
CP
RB
GWB-W
AT
1/2 S
23
Therapist
Nurse
CP
RB
GWB-W
AT
1/2 S
23
Secretary & Waiting
VCT/
RB
GWB-W
AT
Open
CP
Treatment Areas:
GWB1
1/2 S
52
Examination Room
VCT
RB
GWB Lay in
Panels in
Grid
System1
GWB-W1
AT1
Group Therapy Room
CP
RB
1/2 U-M
47
Activities Room and
VCT
RB
GWB
AT
1/2 SS-T
81
Dining Space
GWB-W1
AT1
Quiet Room
CP
RB
1/2 U-M
52
Patient Lockers, Toilets & Showers:
Locker Rooms
VCT
RB
GWB
AT
1/2 S
1
GWB2
Toilets & Showers
CT
CT
CT
AT
1/2 S
1
4'0"
63
Corridors
VCT
RB
GWB
AT
1/2 QQ-T
1
Design and Construction Procedures PG-18-3, Topic 11, "Noise Transmission Control".
2
Full Height ceramic tiles on concrete backer board at tub/ shower with plaster
ceiling.
3
See Section II, "Doors and Hardware".