Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 282
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service - Social Work
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAIN
CEILING
DOOR
H.W.NO.
SYMBOL
GWB-W1
Office, Chief
CP
RB
AT
1/2 S
52
GWB1
Social Worker
VCT/CP
RB
AT
1/2 S
52
GWB1
Associate Social
VCT/CP
RB
AT
1/2 S
52
Worker
Secretary
VCT/CP
RB
GWB
AT
1/2 S-T/
23
Open
Clerk-Typist and/or
VCT/CP
RB
GWB
AT
1/2 S-T
52
Stenographer
Multipurpose Room
CP/VCT
RB
GWB
AT
1/2 U-T
52
Waiting Area
CP
RB
GWB-W
AT
Open
62
Corridors
VCT
RB
GWB
AT
1/2 QQ-T
1
Design and Construction Procedures PG-18-3, Topic 11, "Noise Transmission Control".
2
See Section II, "Doors and Hardware".
121