June 99
construction cost on the COST SUMMARY
SHEET.
F
Construction Document 1 (CD1): This submission
shall include everything required in the DD2
Submission. It differs from the DD2 Submission only
in the level of detail required. Provide a complete
quantity survey estimate. No lump sums will be
permitted without explanation. (Note: Lump sums
shown on Attachment E, CODING AND UNIT
MEASURE CHARTS, are permitted due to summation
of dissimilar items).
VA Design Guide -- National Cemetery Administration
Page 5 -17