June 99
breakdown of the base construction cost, i.e., divided
into 12 major systems. The S2 submittal shall be
broken down to Level "B". Included in both of these
submittals shall be a copy of VA Form CEM-18c, and
PROJECT DATA SHEET NO. 1 with the available
items filled in for the total project as well as for each
building. Alteration costs shall be reported separately
from the cost of new construction.
D. Design Development 1 (DD1): This submission shall
include a two-page VA Form CEM-18c, LEVEL "B"
detail and a PROJECT DATA SHEET NO. 1 with the
available items filled in for the entire project, as well as
separately for each building. A single PROJECT
DATA SHEET No. 2 containing current local labor
rates is also required. Alteration costs shall be
reported separately from the cost for new
construction. Supplement each VA Form CEM-18c
with VA Form CEM-18a or b, which shows the division
of costs between labor and material.
E
Design Development 2 (DD2):
(1) Provide Matrix described in Article 5; VA Form
CEM-18c, COST SUMMARY SHEET, completed
to level "B" detail; VA Form CEM-18b, COST
ESTIMATE WORKSHEETS, to show the division
of costs between labor and material; a detailed
PROJECT DATA SHEET NO. 1 completed in its
entirety with all applicable items filled in for the
entire project as well as separately for each
building; and PROJECT DATA SHEET No. 2
containing local labor rates.
(2) Alteration costs shall be reported separately from
the cost of new construction. The amount of
detail provided in this submission must be
Quantities such as "LS" or "LOT" should be a
minimum.
(3) For proper coding beyond LEVEL "B", the A/E
shall refer to Attachment E, CODING AND UNIT
OF MEASURE REFERENCE CHART.
(4) Asbestos Abatement Estimate: Show total costs
for asbestos abatement provided by the
Professional Industrial Hygienist (PIH) as a
separate cost item below the total base
VA Design Guide -- National Cemetery Administration
Page 5 -16