SPECIAL PROVISIONS
ARTICLE C
SUBMISSION AND COMPLETION SCHEDULE
SPC
1
REVIEW AND COMPLETION SCHEDULE
(a) During the process of the work the Contracting Officer will conduct periodic
reviews with the A/E. The A/E shall perform the work required within the limits of
the following schedule. Professional Architects, Engineers and related design
disciplines familiar with the work shall be provided, as directed by the Contracting
Officer, to attend the VA reviews in the Washington, D.C. office of the Contracting
Officer.
SUBMISSION AND COMPLETION SCHEDULE
ITEM
DATE
DESIGN DEVELOPMENT (1)
Deliver Material to VAMC and Contracting Office
not later than .......................................................................
?
Review Material with VAMC on .............................................
?
Review Material with Contracting Officer on ............................
?
(Payment not to exceed 35% of the total contract amount
at the completion of the review material)
DESIGN DEVELOPMENT (2)
Deliver Material to VAMC and Contracting Officer
not later than ........................................................................
?
Review Material with VAMC on .........................................
?
Review Material with Contracting Officer on ............................
?
(Payment not to exceed 65% of the total contract amount
at the completion of the review material)