(c) Quality Assurance/Quality Control (QA/QC). In an effort to reduce
construction change orders due to design errors and omissions, VA Office of
Facilities Management has initiated a Quality Assurance/Quality Control
program. The A/E shall develop, execute and demonstrate that the project plans
and specifications have gone through a rigorous review and coordination effort.
The requirements are as follows:
(1) Fee Proposal: The A/E shall provide an outline of the
actions that the firm will take during the design process along with
its associated fee.
(2) 2 Weeks after the NTP: The A/E shall submit a detailed
QA/QC Plan describing each step that will be taken during the
development of the various phases of design. Each step should
have an appropriate space where a senior member of the firm can
initial and date when the action has been completed.
(3) 100% Submittal: The A/E shall submit the completed
QA/QC Plan along with the latest marked-up documents (plans,
specifications, etc.) necessary to ensure that a thorough review and
coordination have been completed.
SPA 2
ADDITIONAL REQUIREMENTS
(a) VA Supplied Data. All VA supplied data shall be coordinated and any
variations in design shall be justified in a written report.
(b) Resubmission of the Work. In each submission the A/E shall resubmit the
materials specified in the prior submission, revised according to the comments made
by the VA resulting from the prior review(s).
(c) VA Standards. The A/E shall use VA Program Guides, Design Manuals and
Master Specifications in preparing the Construction Documents for the project.
However, should the A/E determine that deviation from such standards and
specifications is necessary or beneficial to the Government, he shall promptly
submit a request in writing to the Contracting Officer for permission to make the
deviation. The request shall include an explanation of the specific reasons for the
desired change and benefits expected.