(5) Mechanical Design Documents setting forth in detail the mechanical
construction requirements including all mechanical plans, elevations, sections,
details, and schedules for heating, ventilating, air conditioning, refrigeration,
plumbing and sanitary engineering.
(6) Electrical Design Documents setting forth in detail the electrical
construction requirements including all electrical plans, elevations, sections,
details, diagrams and schedules showing transformers, vaults, electrical and
telephone closets, power distribution systems, auxiliary power systems,
switchgear, generator, lighting fixtures, switching power outlets, and signal
system.
(7) Cost Estimate(s) setting forth in detail quantities of materials, labor,
profit, overhead, insurance, taxes, etc. for each separate building within the
project, as well as all site work.
(8) Specifications for all sections of the work utilizing the VA Master
Specification system setting forth in detail all requirements for the
construction fully coordinated with the drawings and other Construction
Documents.
(9)
Presentations and Review Submissions
(b) Project Phasing (CPM). The A/E shall assist the Contracting Officer in
coordinating the development of a CPM (Critical Path Method) network for the
construction of the project. The CPM network shall provide a phasing schedule
which will promote a proper and efficient organization and sequence of
construction. The A/E shall, when directed by the Contracting Officer, serve as an
advisor to the Contracting Officer on all phasing matters. Construction Documents
shall be packaged for bidding and construction in accordance with the CPM
network.