E. NOTES:
1. When only one structural system is possible due to other project
requirements, include an explanatory statement and submit only that structural
system.
2.
Include vertical and lateral load design for CD submission.
3.
Include foundation and fireproofing.
4. Indicate existing utilities and structures within, adjacent, or contiguous to the
new construction.
5. Upon approval of the subsurface investigation criteria, submit qualifications
of at least three consultants being considered for the work together with the
proposal of the consultant recommended as most qualified.
6. If there is only a CD submission, provide a Structural Engineering Analysis
Submission within six weeks from the notice to proceed including sketches,
calculations, and cost estimates of three alternative structural systems for typical
bays, boring location plan for subsurface investigation, and consultant
qualifications. For vertical expansion projects, analyze existing structure for
structural feasibility.
Program Guide, PG-18-15, Volume C
18
May 2006