Where asbestos abatement is required, submit 100% complete asbestos
abatement drawings incorporating comments of the last review.
10. ELECTRICAL
a. Submit all drawings including complete legend symbol list, details, and
schedules. VA Standard Detail sheets may be produced on the drawings.
b. Show all new services to buildings, all new high voltage cable installations,
all manholes, ductlines, transformers, street lighting, grounds lighting, and the high
voltage service point on the electrical plot plan. The utility company must accept the
design of the electrical incoming service in writing. Furnish copies of pertinent
correspondence.
c. Complete the one-line riser diagram including all conduit, cable, ground
wire, and equipment sizes. Nominal transformer impedance shall be indicated.
panelboards schedules. Provide signal, telephone, security, and fire alarm risers;
identify all devices and locations.
d. Complete the building electrical floor plans. Indicate all lighting and power
circuit systems. Show motor protective devices, controller and feeder sizes.
Locate all panels, transformers, and other major electrical components.
11. COST ESTIMATING
a. The A/E shall submit a construction cost estimate in compliance with the
Manual for Preparation of Estimates. The estimate should incorporate all of the
review comments from the previous review. This estimate should include but not be
limited to:
(1) Detailed estimate take-off worksheets
(2) Level "B" S ummary Sheets: For all buildings and sitework
(3) Supplement A to SF 252: For gross building area take-off of all
occupiable buildings.
(4) Project Data Sheets 1 and 2.
(5) Detailed Market analysis.
12. CRITICAL PATH METHOD (CPM)
a. If required, submit the following including VA comments from previous
phasing meetings and Design Development 2 review:
Program Guide, PG-18-15, Volume D
June 1999
Page 38