Spinal Cord Injury Center Design Guide
July 1990 (Rev. Jan. 2004)
Cystoscopic Scrub 28-A
Function:
This space is intended to support the Cystoscopic Room described on the previous sheet. Staff will scrub
here prior to entering the Cysto Room. Visual and voice communication should exist between the two
spaces.
Space Requirement:
30 NSF
Architectural:
Finish Code:
9-A
Floor Finish:
Resilient Sheet*
Base:
Resilient Sheet*
Wall Finish:
Plaster/Special Coating**
Ceiling:
Plaster/Paint
Ceiling Height:
9'-0"
Noise (STC Rating):
N/A
Slab Depression:
None
Special Construction:
-
Hardware:
-
Doors:
None
Windows:
Observation Window, see SD-08110-4.DWG
HVAC:
Temperature:
Summer: 72@50%RH
Winter:
82@30%RH
Min. Air Changes/Hour: 6
Min. % Outside Air:
15%
Pressure:
Negative
% Filtration:
30%(PF)/85%(AF)
Noise Criteria:
40
A/C Loads:
Lights:
75w
Equipment: -
People:
100w, sensible
130w, latent
Electrical:
Lighting Levels:
Gen. Illum: 50fc
Emergency Power:
-