Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 266
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service Human Resources Management
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAIN
CEILING
DOOR
H.W.NO.
SYMBOL
Office, Chief
CP
RB
GWB-W
AT
1/2 S-T
52
Office, Secretary
CP
RB
GWB-W
AT
1/2 S-T
23
Waiting Space
CP
RB
GWB-W
AT
1/2 S-T
52
Office, Asst. Chief
CP
RB
GWB-W
AT
1/2 S-T
23
Office, Personnel
CP
RB
GWB-W
AT
1/2 S-T
23
Management
Specialist
Open Office Space
CP
RB
GWB-W
AT
1/2 S-T
52
GWB1,2
Combination Conf.
AT
1/2 U-T
52
CP
RB
Room/Placement and
Exam Room
Toilet Facilities
CT
CT
GWB
CT
AT
1/2 S
18
4'0"
Storage Area
CP
RB
GWB
AT
1/2 S
13
Active Personnel
CP
RB
GWB
AT
1/2 S-T
13
Records File Area
63
Corridor
CP
RB
GWB
AT
1/2 QQ-T
1
Provide acoustical/tackable wall fabric on one wall.
2
Design and Construction Procedures PG-18-3, Topic 11, "Noise Transmission Control".
88