Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter 206
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service - Canteen
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAINS
CEILING
DOOR
H.W.NO.
SYMBOL
Administrative Service:
Office, Chief1
CP
RB
GWB
AT
1/2 S
23
Office Assistant Chief,
VCT
RB
GWB
AT
1/2 S
23
Food Section
GWB2
VCT
RB
Secured Money Handling
AT
36 S
157
Room1
Administrative Office
VCT
RB
GWB
AT
1/2 S-T
23
Customer Service and Related Storage:
CP
RB
GWB
AT
1/2
Retail Store (Sales
124
Rooms)1
SS-T
ADO3
VCT
RB
GWB
AT
2 SS-T
82
Retail Storage and
Receiving Room1
Dining Area
VCT
RB
GWB-W
AT
1/2
82
SS-T
CT2
Kitchen
QT
QT
AT (SP)
1/2
82
SS-T
CT2
Food Service Area
QT
QT
AT (SP)
1/2 V-T
69
Food Storage Room
VCT
RB
GWB
AT (SP)
1/2 S-T
69
Vending Machine Area
VCT
RB
GWB
AT
1/2 V-T
1
Barber Shop
VCT
RB
GWB-W
AT
1/2
67
S-T
Beauty Shop
VCT
RB
GWB-W
AT
1/2
67
S-T
Ward Cart Storage
VCT
RB
GWB
AT
11/12
69
V-W
Housekeeping Aids Closet
CT
CT
GWB
CT
AT (SP)
1/2 T
13
(SC)
4'0"
1
See Design and Construction Procedures PG-18-3, Topic 14, "Physical Security
Requirements and Options".
2
Full height partition to underside of structure above.
3
See Architectural Design Manual PG-18-10, "Automatic Doors".
30