Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 102
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Intensive Care Units
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAINS
CEILING
DOOR
H.W.NO.
SYMBOL
Stretcher
VCT
RB
GWB
AT
11/12
69
Storage
V-W
Housekeeping
CT
CT
GWB
CT
AT (SP)
1/2 T
13
Aids Closet
(SC)
4'-0"
On-Call Room
CP
RB
GWB-W
AT
1/2 S
23
GWB1
Bath, On-Call
CT
CT
CT
AT
1/2 S
18 or 17
4'-0"
128
Corridor (Suite
VCT
RB
GWB
AT
1/2
129
Entrance)
SS-T/
1/2 X-T
ADO2
1
CT full height at tub on concrete backer.
2
See Architectural Design Manual PG-18-10, Article 3.4, "Automatic Doors".