June 99
"Architectural", "Structural", "Electrical", etc., and earlier Change Order
and Completion Item drawings. The Project Manager shall assign the
drawing numbers. Insert the words, "COMPLETION ITEM NO._______"
above the title block. The VA Project Manager shall assign the Completion
Item numbers and drawing numbers.
(2) Title blocks of Completion Item drawings shall bear the same
project titles and project numbers as the original working drawings. A
sheet title shall appear in the top spaces of the title block. Date the
drawings to reflect the date on which prints and sepias were ordered for
the VA Project Manager.
----------END---------
ATTACHMENT PAGE 5 OF 5