Ceiling Performance Specifications: Design Proposal
2. Methods of achieving tolerance control in fabrication and installation.
3. Job site storage requirements.
4. Construction elevator and/or crane requirements.
5. Installation technique, including trades, equipment, etc.
6. Installation schedule, including time required for each step and
average installation rates in square feet of platform and square feet of
finished ceiling installed per week.
773.2.4
Extra features inherent in the design shall be described. Bidders wishing
to offer components with characteristics not listed in the Specifications
shall describe them so the O/C may provide guidance on their relative
importance as an assistance to preparation of the Priced Proposal.
Bidders intending to submit alternatives with their Priced Proposal shall
submit complete descriptions of them for evaluation.
773.3
OTHER MATERIAL
773.3.1
The Proposal shall include suggestions for detailed test procedures during
the Development Phase, stating which characteristics would be examined
by testing laboratory, mock-up, field prototype, etc. Space will be provided
by the O/C in the hospital under construction for final prototype testing. All
other testing costs will be borne by the Component Contractor.
773.3.2
Bidders who wish to have criteria modified shall submit a description of
any proposed changes not later than (date) . If in the opinion of the
O/C the bidder can show that a change in criteria is justified, the change
might be made. All bidders will be notified of all changes through addenda
to the Specifications. Any modification of the Approved Design during the
Development and Construction Phases will be allowed only by a written
change order from the O/C.
773.3.3
The Proposal shall include a copy of the guarantee to be provided by the
Component Contractor upon completion of his work.