530
Cost Base: Component Costs
Table 530-4.
PARTITIONS COST BREAKDOWN
Dollars per outside gross square foot (except as indicated) adjusted to an
ENR Building Cost Index of 960.
Basic
Doors &
$/sq. ft.
Matr.
Finish
Misc.
Total
of PART.
Miami VAH
Bed-care areas
2.45
2.30
1.20
5.95
5.16
Support Areas
2.74
1.76
1.01
5.51
4.95
Entire Hospital
2.60
1.99
1.10
5.69
5.04
Memphis VAH
Bed-care areas
2.61
2.13
1.40
6.14
4.79
Support Areas
2.07
1.52
1.26
4.85
4.55
Entire Hospital
2.24
1.71
1.31
5.26
4.62
TABLE 530-4a.
PARTITION COST BREAKDOWN,
BASIC MATERIALS
Dollars per outside gross square foot adjusted to an ENR Building Cost
Index of 960.
SP
MC
CC
TOTAL
Miami VAH
Bed-care areas
1.34
1.11
2.45
Support areas
.67
1.62
.45
2.74
Memphis VAH
Bed-care areas
1.65
.96
2.61
Support areas
1.36
.60
.11
2.07
SP
Steel Studs and Plaster
MC
Masonry Core
CC
Concrete Core