through the wall should have a double offset in the form of a Z. The
offset in the Z should be at least 200 mm (8 inches) long.
(b) In a super voltage, or similar room, with thick concrete shield, lead
shielding is not required for ducts penetrating the room wall beyond the
shield inside the room.
(c) Dark
rooms require a full height lead lining. However, the wall
adjacent
to Radiographic or similar rooms the normal lead lining is only 2
m (7 ft)
high. Ducts penetrating this wall above the suspended ceiling may
not need
lead shielding.
3.20 SPD (SUPPLY, PROCESSING AND DISTRIBUTION)
3.20.1 GENERAL
3.20.1.1 See paragraph 2.11.5 for the special exhaust requirements for the
ethylene oxide sterilizer (ETO) and associated items.
3.20.1.2 Provide a dedicated, 100 percent outdoor air, constant volume
air-handling unit to serve the SPD suite.
3.20.2 INDOOR DESIGN CONDITIONS
Summer: 24 degrees C (76 degrees F) Db, 50 percent RH
Winter: 22 degrees C (72 degrees F) Db, 30 percent RH
3.20.3 SUPPLY AIR AND ROOM PRESURE
See Table 3-4.
Table 3-4 Minimum Supply Air and Room Pressure Requirements
Area
Minimum Supply Air
Room Pressure
Changes Per Hour
Administrative Office
4
0
Corridors
4
0
Lounge
6
0
Soiled Decontamination Area
10
Negative
Clean Preparation Area
10
Positive
Lockers, Toilets and Shower
10
Negative
ETO Sterilizer/Aerator Room
10
Negative
Equipment Wash Area
10
Negative
Equipment Room
10
0
Equipment Storage and Testing Room
4
0
ETO Sterilizer Room
10
Negative
General Storage Room
4
0
3.20.4 EMERGENCY POWER REQUIREMENTS
ETO exhaust systems shall be on emergency power.
3.20.5 REFERENCE DOCUMENT
See Design Guide "Supply, Processing and Distribution" for requirements in
individual rooms.
HVAC DESIGN MANUAL
3-21
HVAC REQUIREMENTS FOR OCCUPIED AREAS