13. Define building configuration. Draw sections at the same scale as floor
plans, normally 1:100 (1/8 inch). If the building abuts an existing structure,
indicate in the section how the new floor elevations align with existing.
14. Identify psychiatric areas where special considerations are required to
ensure the safety of patients (e.g. hard ceilings, safety glazing, etc.).
15. Indicate new building components and systems, such as window design,
roofing system, special entryways, building "skin", and any special architectural
elements for the project. Complete detailing of miscellaneous items is not
required for this submission.
16. Indicate all building systems, materials, and future expansion, if applicable.
17. Submit a drawing for all which is part of the construction contract.
18. Provide square meters (feet) of lead paint and x-ray shielding to be removed.
19. Format provided in SPECIFICATIONS. If there is no VA master
specification, develop contract specification that is in compliance with regulations
of the Environmental Protection Agency.