SCHEMATICS
SUBMISSIO
COMPONENTS OF SUBMISSION:
REVIEW FORMAT:
N
MILESTONE
:
S1
Concept Plan Alternatives if not previously developed
Internal VA review;
Schematic Site Development and Analysis
A/E meeting at VACO;
Schematic Block Plans and Narratives
Written comments to A/E
Other specified requirements for interior design,
one week after mtg.
engineering cost estimate and CPM
S2
Schematic Site Development with all comments
Internal VA review;
incorporated
A/E meeting at VACO;
Schematic Architectural Layout with all comments
Written comments to A/E
incorporated
one week after mtg.
Other specified requirements for interior design,
engineering, cost estimate and CPM
DESIGN DEVELOPMENT
SUBMISSIO
N
COMPONENTS OF SUBMISSION:
REVIEW FORMAT:
MILESTONE
:
DD 1
Design Development drawings based on approved
Internal VA review;
Schematic Design or Master Plan
A/E meeting at VACO;
Written comments to A/E
one week after mtg.
DD 2
Final Design Development drawings,
Internal VA review;
specifications and cost estimate with all
A/E meeting at VACO;
comments incorporated
Written comments to A/E
one week after mtg.
CONSTRUCTION DOCUMENTS
SUBMISSIO
N
COMPONENTS OF SUBMISSION:
REVIEW FORMAT:
MILESTONE
:
CD
100% Construction Documents
Internal VA review;
CADD tapes
A/E meeting at VACO;
Written comments to A/E
one week after mtg.
Program Guide, PG-18-15, Volume D
June 1999
Page 3