May 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
CONSTRUCTION DOCUMENTS
ELECTRICAL REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Requirements for Essential Electrical system distribution follow NEC
517-30/517-40 and Electrical Design Manual.
2
Requirements for Primary and Secondary transformation and
distribution equipment (See Electrical Design Manual).
3
Receptacles, mounting heights as required in different areas (See
Electrical Design Manual).
4
Raceways required in Fluoroscopic, Radiographic and Deep Therapy
rooms (See Electrical Design Manual).
5
Raceway systems (See Electrical Design Manual):
a. Install all wiring in raceways.
b. Encase underground raceways in concrete.
c. Install isolated power systems wiring in plastic coated conduits.
6
Alarms: Nonflammable medical gas and medical- surgical vacuum
systems (See Electrical Design Manual) and NFPA 99:
a. Master alarm panels required at the telephone switchboard and
engineering control center or boiler plant.
b. Area alarms provided at nurses stations where medical gas
systems are installed.
7
Miscellaneous Alarms (See Electrical Design Manual), such as Blood
Bank refrigeration, Medical Gas System Alarm and others.
8
Remote Dictating System: Dial-Link or Direct-wired (See Electrical
Design Manual) for new hospitals and laboratory service areas.
9
Lightning Protection System (See Electrical Design Manual). Use the
Risk Assessment Guide, Appendix H of the NFPA780 in determine the
requirement.
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
8