Process
Need a Sign Program
Engage a qualified manufacturer and installer
Purchasing Objective
Bidding and entering into a What is looking to be accomplished.
contract for manufacturing and
installation. Environmental Graphic
Assist in the pricing process by answering
questions and providing clarifications
Design Firm Tasks
What is being done by the
Environmental Graphic Design firm.
Form 90-2237
Documentation
What is being delivered.
Statement of Work
Estimate
Contracting Officer conducts the purchasing
VA Project Management
process.
Tasks
What is being done by the VA.
Pricing Abstract
Approvals
What approvals need to be achieved.
Technical Team
Contractor Qualifications
Grade Review
This phase will take 4 to 10 weeks.
Time
What is the time required.
Defining what work is to be accomplished
Demolition Objective
Removal of existing sign What is looking to be accomplished.
regarding removal of existing signs
program
Develop documentation
Environmental Graphic
Design Firm Tasks
What is being done by the
Environmental Graphic Design firm.
Documentation describing the scope of demolition
Documentation
What is being delivered.
work. This can consist of photographs, description
of work and plans not location of signs to be
removed
Provide direction on the scope of demolition to be
VA Project Management
addressed.
Tasks
What is being done by the VA.
Review demolition documentation.
Review sign removal schedule and plan providing
comment and revisions.
VA approval of demolition documents
Approvals
What approvals need to be achieved.
2 to 4 weeks
Time
What is the time required.
02/2005