Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapters - 800 thru 870
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Services - VBA Regional Offices
ROOM OR SPACE
FINISHES
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAIN
CEILING
DOOR
H.W.NO.
SYMBOL
All areas in Chapters 800 through 870 that utilize the open office planning concept
CP
RB
GWB
AT
The following spaces in Chapters 800 through 870 will be private (i.e. enclosed):
CHAPTER 800 - OFFICE OF DIRECTOR
Office, Director
CP
RB
GWB-W
AT
1/2 H
23
Office, Assistant
CP
RB
GWB-W
AT
1/2 H
23
Director
GWB-W1,2
Administrative
CP
RB
AT
1/2 J-T
40
Conference Room
Director's Toilet
CT
CT
GWB-W
CT
AT
1/2 H
1
4'-0"
CHAPTER 801 - BUILDING SUPPORT FACILITIES
Toilet Facilities
CT
CT
GWB(SC)
CT
AT
1/2 H
1
4'0"
Storage Room
VCT
RB
GWB
AT
11/12
69
HH-W
11/12
13
K-W
Housekeeping Aids
CT
CT
GWB(SC)
CT
AT
1/2 K
13
Closet
4'0"
CHAPTER 802 - DISTRICT COUNSEL
Office, District
CP
RB
GWB-W
AT
1/2 H
23
Counsel
Office, Assistant
CP
RB
GWB-W
AT
1/2 H
23
District Counsel
Office, General
CP
RB
GWB-W
AT
1/2 H
23
Attorneys
Library
CP
RB
GWB-W
AT
1/2 J-T
40
CHAPTER 821 - ADJUDICATION DIVISION
Office, Division Chief
CP
RB
GWB-W
AT
1/2 H
23
Office, Assistant
CP
RB
GWB-W
AT
1/2 H
23
Division Chief
1
See Design and Construction Procedures PG-18-3, Topic 11, "Noise Transmission Control".
2
One wall to receive acoustical/ tackable wall surface.
153