Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 701
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service - Cemetery
ROOM OR SPACE
FINISHES
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAIN
CEILING
DOOR
H.W.NO.
SYMBOL
Administration Building:
Offices
CP
RB/WD
GWB-W
AT/GWB
1/2 H
23
Operational Center
CP
RB/WD
GWB-W
AT/GWB
1/2 V-T
52
Lunch Room
VCT
RB
GWB-W
AT/GWB
1/2 H-T
52
Storage
RSF
RSF
GWB
AT
1/2 K-T
13
Housekeeping Aids
RSF
RSF
GWB
CT
AT (SP)
1/2 J
13
Closet
(SC)
4'0"
/GWB
Multipurpose Room
CP
RB/WD
GWB-W
AT/GWB
1/2 H
52
(Conference Room)
Lobby & Reception1
Special
1/2 JJ-T
81
Toilet
CT
CT
GWB
CT
AT/GWB
1/2 H
1
(SC)
4.0
142
Public Toilet, Exterior
LM
LM
CMU
AT (SP)
1/2 H
(SC)
/EXP
43
Corridor
VCT
RB
GWB
AT
1/2 K-T
1
Finishes are be selected on the basis of architectural requirements and cost
considerations. Floor to be hard surface material such as: QT, STONE, BRICK, SLATE,
TERRAZO, etc.
2
Use H.W. No. 14 for single use and 1 for multi-use.
3
See Section II, "Doors and Hardware".
151